In 2005, Seacoast Utility Authority (SUA), located in Palm Beach County, Florida, evaluated
options for expanding their two existing water treatment plants to meet future demands, and for
converting their plants from lime softening facilities to membrane softening facilities. SUA commissioned a
preliminary design evaluation to study various options for expanding their existing water treatment plants to
meet future demands and for converting the plants from lime softening facilities to membrane softening
facilities. This report included a description of the process and components required for each option
evaluated, a proposed schedule to implement the improvements, design considerations for the improvements,
as well as the estimated capital and operation and maintenance costs for each option. These options were based on existing
facilities, water demands and plant capacities, water quality, water treatment regulations, concentrate disposal
options, and permitting requirements. Includes tables.