1.1
This guide identifies pipeline components, recommended protocols and evaluation criteria to consider in the inspection and acceptance of installed thermoplastic pipe by either person-entry, or remote inspection.
1.2
This guide is intended for installation related observations and assumes that pre-installation inspection has been completed and all final settlement of fill has occurred. Inspection should be a minimum of 30 days after installation. This inspection period could be increased to accommodate the installer’s warranty period, which is typically one year or greater.
Note 1:
Pipe types covered under this standard are typically installed under the AASHTO LRFD Bridge Construction Specifications or Practice
D2321
.
1.3
It applies to the thermoplastic non-pressure gravity flow storm and sewer pipe manufactured in accordance with Specifications
D3034
,
F679
,
F714
,
F794
,
F894
,
F949
,
F1803
,
F2306
,
F2435
,
F2562
,
F2648
,
F2763
,
F2764
,
F2881
,
F2947
,
F3123
, ISO 21138, ISO 4435, ISO 8772 and ISO 8773. It may also be considered for use for any similar thermoplastic pipe products not covered by this list but with similar physical or performance characteristics if approved by the owner. This guide does not supersede any regulatory requirements, project specifications, or any of the requirements in the noted thermoplastic storm and sewer standards.
1.4
Person entry is normally used unless extenuating circumstances preclude this type inspection by the engineer. Remote inspection is recommended for use for pipe diameters of 30 in. [750 mm] and smaller unless otherwise specified by owner or engineer. Person entry ultimately depends on the safety, size, and environmental consideration assessments by the engineer.
1.5
Access of installed pipe for manual inspection should follow OSHA 29 CFR PART 1926 SUBPART AA or ISO 45001, or any other applicable regulations for confined space entry. This standard does not purport to address all of the safety concerns, if any, associated with its use. It is the responsibility of the user of this standard to establish appropriate safety and health practices and determine the applicability of regulatory limitations prior to use.
1.6
The values stated in either SI units or inch-pound units are to be regarded separately as standard. The values stated in each system are not necessarily exact equivalents; therefore, to ensure conformance with the standard, each system shall be used independently of the other, and values from the two systems shall not be combined.
1.7
This standard does not purport to address all of the safety concerns, if any, associated with its use. It is the responsibility of the user of this standard to establish appropriate safety, health, and environmental practices and determine the applicability of regulatory limitations prior to use.
1.8
This international standard was developed in accordance with internationally recognized principles on standardization established in the Decision on Principles for the Development of International Standards, Guides and Recommendations issued by the World Trade Organization Technical Barriers to Trade (TBT) Committee.
====== Significance And Use ======
4.1
The inspection of installed thermoplastic storm and sewer pipe verifies proper installation of the product and establishes a baseline for comparison for further evaluation.
4.2
This guide is useful as a reference by an owner in preparing project specifications and to identify, evaluate and interpret observations during post installation inspections of pipe.
4.3
Field evaluations either remotely or with person entry should be made by an independent 3rd party engineering firm or duly appointed representative of the owner.