Measurement methods for building — Setting-out and measurement — Part 1: Planning and organization, measuring procedures, acceptance criteria
建筑材料的测量方法——放线和测量第1部分:计划和组织、测量程序、验收标准
Deals with the different stages of the setting out work, i.e. the measuring of the primary framework (traverses, grids, etc.) on the site, the setting out of reference lines (baselines), the transfer (plumbing up) of reference lines to other floors, the setting out of position points and the levelling procedure for these different stages. Gives values for permissible deviations when measuring and setting out and recommends certain procedures and instruments to be used.