Standard Practice for Infiltration and Exfiltration Acceptance Testing of Installed Precast Concrete Pipe Sewer Lines (Metric)
已安装的预制混凝土排水管的渗透和渗出验收试验的标准实施规程(米制)
1.1
This practice covers procedures for testing installed precast concrete pipe sewer lines using either water infiltration or exfiltration acceptance limits to demonstrate the integrity of the installed materials and construction procedure.
1.2
This practice is the SI companion of Practice
C969
.
Note 1:
The owner shall specify the following: who will conduct, observe, and furnish labor, furnish material and measuring devices, and pay for the tests; who is responsible for determining local groundwater conditions; and which test is to be conducted, that is, an infiltration test or an exfiltration test.
Note 2:
The user of this practice is advised that test criteria presented in this practice are similar to those in general use. Pipe, 600-mm diameter or larger, may be accepted by visual inspection when testing for infiltration.
1.3
This standard does not purport to address all of the safety concerns, if any, associated with its use. It is the responsibility of the user of this standard to establish appropriate safety and health practices and determine the applicability of regulatory limitations prior to use.
1.4
This international standard was developed in accordance with internationally recognized principles on standardization established in the Decision on Principles for the Development of International Standards, Guides and Recommendations issued by the World Trade Organization Technical Barriers to Trade (TBT) Committee.
====== Significance And Use ======
5.1
This is not a routine test. The values recorded are applicable only to the sewer being tested and at the time of testing.